DEVELOPMENT OF AL ANSAB
WETLAND AND HAYA WATER HEADQUARTER CAR PARK
TENDER NO. 258/2009
SYNOPSIS OF SCOPE
This Contract involves the following general
activities:
• Excavate and dispose contaminated
soil from Waste Lagoon ‘A’ to approved tip
off.
• Earth work cut and fill required to
grade FGL to +49.15m.
• Slope protection works for
embankments
• Construction of shaded seating
arrangement for visitors, 2 months from
start of the project
• Construction of shaded parking for
two buses and five golf carts
• Construction of access road to
wetland site office to be within 3 weeks
from start of the project
• Construction of access path for
golf carts from visitor’s park to the
wetland temporary site office to be done in
1 month time from start of the project
• Disposal of contaminated soil from
Lagoon A
• Supply and installation of area
lights including cables and panels.
• Construction of drainage system for
the car park area.
• Landscaping for the car park,
visitors park area, Park and buffer zone.
• Design and construct irrigation
system suitable and adequate for the
landscape area.
• Works other than the above but
detailed in the tender drawings, Bill of
quantities and specifications.